May 10, 2019 Update

After a successful foundation pour on the Mission Street tower, we are now forming and pouring the walls and floors that will make up the below grade levels of this exciting project. We are close to reaching the bottom of the excavation for the First Street tower and excavation activities will continue 24 hours a day on the our site.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

 

Emergency Contact:

Mitchell Engineering

1395 Evans Ave

San Francisco, Ca. 94124

415/589-7317 24-Hour Contact

 

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948