March 27, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from April 8, 2020 through April 29, 2020 starting at 2:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions and stay safe.

Emergency Contact:
Swinerton I Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

March 13, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

 

This notice is to confirm upcoming night work in the area beginning in two weeks. Mitchell will continue site utility work for the Oceanwide Center development. This includes the installation of storm drain laterals and other site utilities along First Street. High impact noise is expected from 8PM-12AM followed by low impact noise from 12AM-6AM. Please note that this work is required to be performed in the evenings to reduce the impacts on vehicular traffic on First St. We will keep you updated with more information as this work is scheduled.

 

We appreciate your support and please do not hesitate to reach out should you have questions.

 

Emergency Contact:

 

Mitchell Engineering
1395 Evans Ave
San Francisco, CA. 94124
(415) 589-7317 24-Hour Contact

 

Swinerton I Webcor Joint Venture

24-Hour hotline at (415) 746-9948

 

Thank you.