February 14, 2020 Update

Happy Valentines Day from the team at Oceanwide Center.

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from February 18, 2020 through mid-March starting at 2:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Swinerton I Webcor Joint Venture

24-Hour hotline – (415) 746-9948