Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from April 8, 2020 through April 29, 2020 starting at 2:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.