Feb 14, 2019 Update

The activity next week will remain similar the previous weeks. Excavation will continue 24 hours a day on the First Street site and we will continue preparing the foundation of the Mission Street site.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

We are aware of the inconvenience caused by our activity and apologize in advance. Please rest assured that we will do everything possible to minimize the impact of our activities. If you have particular concerns (scheduled deliveries, construction questions, accessibility needs, etc.) that must be addressed, please see contact information below. We will do everything possible to find a mutually agreeable solution.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Mitchell Engineering
1395 Evans Ave
San Francisco, Ca. 94124

415-589-7317 24-Hour Contact

 

Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Feb 1, 2019 Update

The activity next week will remain similar the previous weeks. Excavation will continue 24 hours a day on the First Street site and we will continue preparing the foundation of the Mission Street site.

Mitchell Engineering will continue Site Utility work for the Oceanwide Center development. The work includes the installation of single storm drain lateral on First Street between Mission and Stevenson Streets. High impact noise is expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

We are aware of the inconvenience caused by our activity and apologize in advance. Rest assured that we will do everything possible to minimize the impact of our activities. If you have particular concerns (scheduled deliveries, construction questions, accessibility needs, etc.) that must be addressed, please see contact information below. We will do everything possible to find a mutually agreeable solution.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

 

Emergency Contact:

Mitchell Engineering

1395 Evans Ave

San Francisco, Ca. 94124

415/589-7317 24-hour Contact

 

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948

Jan 23, 2019 Update

Mitchell Engineering will continue Site Utility work for the Oceanwide Center development starting next week. The work includes the installation of single storm drain lateral on First Street between Mission and Stevenson Streets. High impact noise is expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

We are aware of the inconvenience caused by our activity and apologize in advance. Rest assured that we will do everything possible to minimize the impact of our activities. If you have particular concerns (scheduled deliveries, construction questions, accessibility needs, etc.) that must be addressed, please see contact information below. We will do everything possible to find a mutually agreeable solution.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

 

Emergency Contact:

Mitchell Engineering

1395 Evans Ave

San Francisco, Ca. 94124

415/589-7317 24-hour Contact

 

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948

Jan 10, 2019 Update

Happy New Year! We have completed the excavation on the Mission Street site and are preparing the site for foundation work. We expect large concrete pours for our foundation to begin in March. Excavation on the First Street site is progressing and will continue over the next several months. We will continue to operate on site 24 hours per day during this time.

PG&E has completed their night work on the corner of Second Street and Mission Street. Our next planned night work will be for utility connections along First Street and we will provide you with a more detailed schedule in the coming weeks.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948

Feb 22, 2018 Update

Beginning this weekend and continuing next weekend, (2/24-2/25, 3/3-3/4), we will be installing overhead pedestrian and vehicular protection on Ecker between Jessie and Mission Street next to the work site. This will require the full closure of Ecker to vehicular traffic for both weekends from 7:00 am – 5:00 pm. Ecker will continue to remain open to pedestrians at all times.

The installation of our deep foundation will continue to be a 24-hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock.

Feb 16, 2018 Update

The construction site will be closed down this weekend, including Monday, for Presidents’ Day.

The installation of our deep foundation will continue to be a 24-hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. This work will be most noticeable at various times over the next 6 weeks when the drilled foundations are installed on the 1st Street site. Neighbors should notice a reduction in noise starting around mid-March.

In late February, we will begin installing overhead pedestrian and vehicular protection on Ecker between Jessie and Mission Street next to the work site. This will require the full closure of Ecker to vehicular traffic for two weekends during the day. Ecker will continue to remain open to pedestrians at all times. Once the timeline is confirmed, notification regarding timing will be posted.

Feb 1, 2018 Update

The installation of our deep foundations will continue to be a 24-hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. This work will be most noticeable at various times over the next 6 weeks when the drilled foundations are installed on the 1st Street site. Neighbors should notice a reduction in noise starting around mid-March.

In mid-February we will begin installing overhead pedestrian and vehicular protection on Ecker between Jessie and Mission Street next to the work site. Exact dates are to be determined but this will likely require the full closure of Ecker to vehicular traffic for two weekends during the day. Ecker will continue to remain open to pedestrians at all times.

Over the next several weeks, Oceanwide’s contractors will continue the installation of the perimeter shoring wall on First Street. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

Jan 22, 2018 Update

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. This will continue to be a 24 hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, and we apologize for any inconvenience.

Oceanwide’s contractors have completed installation of the perimeter shoring wall directly behind One Ecker and they will continue the installation on the First Street side. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During this time, please feel free to contact the project’s general superintendent, Dave Thompson, directly at (406) 580-0152 or the 24-Hour hotline at (415) 746-9948.

Jan 8, 2018 Update

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. This will continue to be a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, and we apologize for any inconvenience.

Oceanwide’s contractors have completed installation of the perimeter shoring wall directly behind One Ecker and they will continue the installation on the First Street side. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During this time, please feel free to contact the project’s general superintendent, Dave Thompson, directly at (406) 580-0152 or the 24-Hour hotline at (415) 746-9948.

Dec 21, 2017 Update

Happy Holidays!  Oceanwide’s contractors will not be working the evening of December 23rd through the morning of December 26th and the evening of December 29th through the morning of January 2nd.

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. Unfortunately, this will continue to be a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, and we apologize for any inconvenience.

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site and is now on Stevenson and Ecker. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours.  Every effort will be made to minimize the impacts to all neighbors during this time.

Oceanwide’s contractors will continue minor demolition work on the southern part of Ecker Street between Mission and Elim. This work is preparation for installing overhead protection that is required for safe pedestrian passage down Ecker during construction.

During this time, please feel free to contact the project’s general superintendent, Dave Thompson, directly at (406) 580-0152 or the 24-Hour hotline at (415) 746-9948.