April 28, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from May 12, 2020 through early June starting at 2:00 a.m. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions and stay safe.

Emergency Contact:
Swinerton I Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

March 27, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from April 8, 2020 through April 29, 2020 starting at 2:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions and stay safe.

Emergency Contact:
Swinerton I Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

March 13, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

 

This notice is to confirm upcoming night work in the area beginning in two weeks. Mitchell will continue site utility work for the Oceanwide Center development. This includes the installation of storm drain laterals and other site utilities along First Street. High impact noise is expected from 8PM-12AM followed by low impact noise from 12AM-6AM. Please note that this work is required to be performed in the evenings to reduce the impacts on vehicular traffic on First St. We will keep you updated with more information as this work is scheduled.

 

We appreciate your support and please do not hesitate to reach out should you have questions.

 

Emergency Contact:

 

Mitchell Engineering
1395 Evans Ave
San Francisco, CA. 94124
(415) 589-7317 24-Hour Contact

 

Swinerton I Webcor Joint Venture

24-Hour hotline at (415) 746-9948

 

Thank you.

February 14, 2020 Update

Happy Valentines Day from the team at Oceanwide Center.

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from February 18, 2020 through mid-March starting at 2:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Swinerton I Webcor Joint Venture

24-Hour hotline – (415) 746-9948

January 15, 2020 Update

Happy New Year from the team at Oceanwide Center. Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from January 29, 2020 through late February starting at 2:00 am. Unfortunately, this is a 24-hour-a-day operation as this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

December 27, 2019 Update

Greetings from the team at Oceanwide Center. We hope you all had a wonderful and safe holiday!

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the evenings through the early morning hours as we pour the basement walls for the First St. tower. Concrete placement of suspended decks will be taking place from December 30, 2019 through January 9, 2020 starting at 2:00 am.

The SF Water Department will be installing a new fire hydrant on Jessie St. and Anthony St. This work will take place during the evenings for the next few weeks depending on the schedule from the Water Department. We will make sure to keep you updated on this activity.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

December 4, 2019 Update

We hope you all had a wonderful Thanksgiving Holiday! Below are some important updates regarding the Oceanwide Center project.

The SF Water Department will be installing a new fire hydrant on Jessie St. and Anthony St. This work will take place during the evenings for the next few weeks depending on the schedule from the Water Department.

Additionally we will continue to work on site in the evenings as we pour the basement walls for the First St. tower. Concrete placement of upturned pile cap (UPC) foundations will be taking place from December 6th to December 16th from 2:00 am to 7:00 am.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Mitchell Engineering
1395 Evans Ave
San Francisco, CA 94124
(415) 589-7317 24-Hour Contact

Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

November 22, 2019 Update

Happy Holidays from our team here at Oceanwide Center!

This notice is to confirm upcoming night work in the area. The SF Water Department will be installing a new fire hydrant on Jessie St. and Anthony St.  This work will take place during the evenings for the next few weeks depending on the schedule from the Water Department.

Additionally, we will continue to work on site in the evenings as we pour the basement walls for the First St. tower. Concrete placement of upturned pile cap (UPC) foundations will be taking place from November 25, 2019 to December 5, 2019 from 2:00 am to 7:00 am.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Mitchell Engineering
1395 Evans Ave
San Francisco, CA 94124
(415) 589-7317 24-Hour Contact


Swinerton I Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

November 7, 2019 Update

Greetings from our team at Oceanwide Center!

On Oct 15, 2019, Oceanwide Center LLC announced that work on the Mission Street tower will suspend until further notice; however, work continues on the First Street tower without interruption. The First Street tower comprises of 1.05 million-square-feet of office and 109 residential condos. It is slated to reach 910 feet and become the second tallest in San Francisco after Salesforce Tower. Since the Oct 15 announcement, the First Street tower work has reached the important milestone of completing the basement structural mat foundation.

Despite the planned suspension, the Mission Street tower footprint remains a construction site, and continues to be actively managed by our construction team. All safety measures remain in place to ensure public safety around the jobsite.

In other project news, The SFPUC will be adding a new fire hydrant on the Jessie Street at Anthony Street later this month. This work will be done by Mitchell Engineering in the evenings starting on November 18th.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Mitchell Engineering
1395 Evans Ave
San Francisco, CA 94124
(415) 589-7317 24-Hour Contact


Swinerton I Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

October 10, 2019 Update

Greetings from our team at Oceanwide Center! Activities will continue 24 hours a day on the site as we prepare for our next major concrete foundation pour for the First Street tower. This concrete pour will start the evening of Friday October 11th at 10:00PM and end Saturday October 12th at approximately 1:00PM. Ecker Street between Jessie Street and Mission Street will be closed to traffic during this time. 

On Sunday, October 13th we will be erecting an additional tower crane to support the construction of the First Street tower. No additional street closures are planned for this activity.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Swinerton I Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.