August 12, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

The overhead protection and vehicle barrier have been removed along Ecker. Concrete chipping will be taking place on the Mission Street tower site during the daytime hours for the next few weeks. This work is necessary to remove the temporary steel piles that were placed during the construction of the below grade walls and foundation.

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs and continue to bring the project up to street level on the First Street tower. Concrete placement of suspended decks will be taking place on September 3rd, 8th, 14th, 18th and 23rd starting at 1:00 am.

Deliveries of structural steel will continue during this time. Transportation permits require that these deliveries be made between midnight at 6:30 am. We will continue to make every effort to minimize these impacts on the surrounding neighbors and we appreciate your continued support.

Please do not hesitate to reach out should you have questions and please stay safe.

Emergency Contact:
Swinerton | Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

June 30, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs and continue to bring the project up to street level. Concrete placement of suspended decks will be taking place on July 16th, 17th, 28th and 31st starting at 3:00 am. Deliveries of structural steel will begin on July 20th and continue through August 24th. Transportation permits require that these deliveries be made between midnight at 6:30 am. We will continue to make every effort to minimize these impacts on the surrounding neighbors and we appreciate your continued support.

Please do not hesitate to reach out should you have questions and please stay safe.

Emergency Contact:
Swinerton | Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

June 4, 2020 Update

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs and continue to bring the the project up to street level by late summer. Concrete placement of suspended decks will be taking place from June 23rd through mid-July starting at 3:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions and stay safe.

Emergency Contact:
Swinerton | Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

April 28, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from May 12, 2020 through early June starting at 2:00 a.m. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions and stay safe.

Emergency Contact:
Swinerton I Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

March 27, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from April 8, 2020 through April 29, 2020 starting at 2:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions and stay safe.

Emergency Contact:
Swinerton I Webcor Joint Venture
24-Hour hotline – (415) 746-9948

Thank you.

March 13, 2020 Update

Below are some important updates regarding the Oceanwide Center project:

 

This notice is to confirm upcoming night work in the area beginning in two weeks. Mitchell will continue site utility work for the Oceanwide Center development. This includes the installation of storm drain laterals and other site utilities along First Street. High impact noise is expected from 8PM-12AM followed by low impact noise from 12AM-6AM. Please note that this work is required to be performed in the evenings to reduce the impacts on vehicular traffic on First St. We will keep you updated with more information as this work is scheduled.

 

We appreciate your support and please do not hesitate to reach out should you have questions.

 

Emergency Contact:

 

Mitchell Engineering
1395 Evans Ave
San Francisco, CA. 94124
(415) 589-7317 24-Hour Contact

 

Swinerton I Webcor Joint Venture

24-Hour hotline at (415) 746-9948

 

Thank you.

February 14, 2020 Update

Happy Valentines Day from the team at Oceanwide Center.

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from February 18, 2020 through mid-March starting at 2:00 am. This activity involves night work because this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Swinerton I Webcor Joint Venture

24-Hour hotline – (415) 746-9948

January 15, 2020 Update

Happy New Year from the team at Oceanwide Center. Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the early morning hours as we pour the basement walls and floor slabs for the First St. tower. Concrete placement of suspended decks will be taking place from January 29, 2020 through late February starting at 2:00 am. Unfortunately, this is a 24-hour-a-day operation as this type of foundation requires large monolithic concrete pours to ensure structural integrity.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

December 27, 2019 Update

Greetings from the team at Oceanwide Center. We hope you all had a wonderful and safe holiday!

Below are some important updates regarding the Oceanwide Center project:

We will continue to work on site in the evenings through the early morning hours as we pour the basement walls for the First St. tower. Concrete placement of suspended decks will be taking place from December 30, 2019 through January 9, 2020 starting at 2:00 am.

The SF Water Department will be installing a new fire hydrant on Jessie St. and Anthony St. This work will take place during the evenings for the next few weeks depending on the schedule from the Water Department. We will make sure to keep you updated on this activity.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

December 4, 2019 Update

We hope you all had a wonderful Thanksgiving Holiday! Below are some important updates regarding the Oceanwide Center project.

The SF Water Department will be installing a new fire hydrant on Jessie St. and Anthony St. This work will take place during the evenings for the next few weeks depending on the schedule from the Water Department.

Additionally we will continue to work on site in the evenings as we pour the basement walls for the First St. tower. Concrete placement of upturned pile cap (UPC) foundations will be taking place from December 6th to December 16th from 2:00 am to 7:00 am.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Mitchell Engineering
1395 Evans Ave
San Francisco, CA 94124
(415) 589-7317 24-Hour Contact

Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.