October 10, 2019 Update

Greetings from our team at Oceanwide Center! Activities will continue 24 hours a day on the site as we prepare for our next major concrete foundation pour for the First Street tower. This concrete pour will start the evening of Friday October 11th at 10:00PM and end Saturday October 12th at approximately 1:00PM. Ecker Street between Jessie Street and Mission Street will be closed to traffic during this time. 

On Sunday, October 13th we will be erecting an additional tower crane to support the construction of the First Street tower. No additional street closures are planned for this activity.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Swinerton I Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you.

October 3, 2019 Update

Greetings from our team at Oceanwide Center! Activities will continue 24 hours a day on the site as we prepare for our next major concrete foundation pour for the First Street tower. This concrete pour will start the evening of Friday October 4th at 10:00PM and end Saturday October 5th at approximately 1:00PM. Ecker Street between Jessie Street and Mission Street will be closed to traffic during this time.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Swinerton I Webcor Joint Venture

24-Hour hotline at (415) 746-9948

Thank you.

August 23, 2019 Update

This weekend we will be erecting the second of our three tower cranes here at Oceanwide Center. This will be contained within our site and we expect little to no disruption of normal traffic. Activities will continue 24 hours a day on the our site as we prepare for our next major concrete foundation pours for the First Street tower. These concrete pours are scheduled for 9/7/19 and 9/21/19. We will provide additional details on potential traffic impacts as we get closer to these dates.

Mitchell Engineering will also continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Mitchell Engineering
1395 Evans Ave
San Francisco, Ca. 94124
415/589-7317 24-Hour Contact

Swinerton I Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you

July 31, 2019 Update

Oceanwide Center is approaching another major milestone, the foundation pour for the First Street tower! Activities will continue 24 hours a day on the our site. We are also hard at work building out the basement levels of the Mission Street tower.

The west sidewalk on First Street between Stevenson and Mission Streets will be closed to pedestrians late this Friday evening (8/3/19) through Saturday afternoon (8/4/19). We appreciate your cooperation as we will be pouring the northeastern corner of the building foundation. 

Mitchell Engineering will also continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Mitchell Engineering
1395 Evans Ave.
San Francisco, CA. 94124

415/589-7317 24-Hour Contact

Swinerton I Webcor Joint Venture
24-Hour hotline at (415) 746-9948

June 27, 2019 Update

Happy SF Pride from the team at Oceanwide Center!

The 2019 SF Pride Parade will take place this Sunday, June 30th, 2019 at 10:30AM The parade route will run on Market Street from Embarcadero to Civic Center. For complete details please visit http://www.sfpride.org/parade/.

Oceanwide Center is close to reaching the bottom of the excavation for the First Street tower and excavation activities will continue 24 hours a day on the our site. We will be planning a large foundation pour for the end of July and we will provide more specific details as that activity approaches. We are also hard at work building out the basement levels of the Mission Street tower.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:
Mitchell Engineering
1395 Evans Ave
San Francisco, Ca. 94124
415/589-7317 24-Hour Contact

Swinerton I Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Thank you

May 31, 2019 Update

Oceanwide Center is close to reaching the bottom of the excavation for the First Street tower and excavation activities will continue 24 hours a day on the our site. We are also hard at work building out the basement levels of the Mission Street tower.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

 

Emergency Contact:

Mitchell Engineering

1395 Evans Ave

San Francisco, Ca. 94124

415-589-7317 24-Hour Contact

 

Swinerton | Webcor Joint Venture

24-Hour hotline at 415-746-9948

May 10, 2019 Update

After a successful foundation pour on the Mission Street tower, we are now forming and pouring the walls and floors that will make up the below grade levels of this exciting project. We are close to reaching the bottom of the excavation for the First Street tower and excavation activities will continue 24 hours a day on the our site.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

 

Emergency Contact:

Mitchell Engineering

1395 Evans Ave

San Francisco, Ca. 94124

415/589-7317 24-Hour Contact

 

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948

Apr 18, 2019 Update

There will be a temporary closure of Ecker Street between Jessie Street and Mission Street this Saturday, April 20th from 7:00AM to 5:00PM. Our team will be replacing the overhead protection that was temporarily removed during the large concrete pour for the Mission Street tower foundation. Other activity on site will remain very similar the previous weeks. Excavation will continue 24 hours a day on the First Street site.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Mitchell Engineering
1395 Evans Ave
San Francisco, Ca. 94124
415/589-7317 24-Hour Contact

Swinerton | Webcor Joint Venture
24-Hour hotline at (415) 746-9948

Mar 29, 2019 Update

This is a reminder that Oceanwide Center will be pouring the foundation mat slab for the Mission Street tower on Friday March 29 and Saturday March 30. During this time the area will experience heavy traffic with the trucks needed for this massive concrete pour. We will always try to perform this work with as little disruption as possible to the neighborhood and we want to make the community aware of some important dates below. We are continuing to work closely with with the City and County of San Francisco to minimize these impacts to the greatest extent possible. Jessie St and the portion of Ecker St between Jessie St and Mission St will be closed to traffic from Friday evening until Saturday evening.

Other activity on site will remain very similar the previous weeks. Excavation will continue 24 hours a day on the First Street site.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

 

Emergency Contact:

Mitchell Engineering

1395 Evans Ave

San Francisco, Ca. 94124

415/589-7317 24-Hour Contact

 

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948

 

Thank you.

 

 

Mar 15, 2019 Update

We are very excited as the Oceanwide Center project approaches another major milestone at the end of this month. We will be pouring the foundation mat slab for the Mission Street tower on Friday March 29th and Saturday March 30th. During this time the area will experience heavy traffic with the trucks needed for this massive concrete pour. We will always try to perform this work with as little disruption as possible to the neighborhood and we want to make the community aware of some important dates below. We are continuing to work closely with with the City and County of San Francisco to minimize these impacts to the greatest extent possible. We also want to remind everyone that this Saturday March 16th, San Francisco will host it’s annual St. Patrick’s Day Parade. Please click here for details on the parade route and impacted streets. 

The overhead protection along Ecker Street street will be temporarily removed the weekend of March 23rd in preparation for the foundation pour of the Mission Street tower. It will be reinstalled the weekend after the foundation pour is completed. Jessie Street and Ecker Street will be closed to through traffic on Saturday March 23rd, Friday March 29th, Saturday March 30th, and Saturday April 6th.

Other activity on site will remain very similar the previous weeks. Excavation will continue 24 hours a day on the First Street site.

Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals on First Street and on Stevenson Streets. High impact noise is continued to be expected from 8:00PM to 12:00AM, followed by low impact noise from 12:00AM to 6:00AM.

Your cooperation will help this project become a success for your neighborhood and the City of San Francisco. Thank you in advance for your understanding and cooperation.

Please do not hesitate to reach out should you have questions.

 

Emergency Contact:

Mitchell Engineering

1395 Evans Ave

San Francisco, Ca. 94124

415/589-7317 24-Hour Contact

 

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948