Feb 22, 2018 Update

Beginning this weekend and continuing next weekend, (2/24-2/25, 3/3-3/4), we will be installing overhead pedestrian and vehicular protection on Ecker between Jessie and Mission Street next to the work site. This will require the full closure of Ecker to vehicular traffic for both weekends from 7:00 am – 5:00 pm. Ecker will continue to remain open to pedestrians at all times.

The installation of our deep foundation will continue to be a 24-hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock.

Feb 16, 2018 Update

The construction site will be closed down this weekend, including Monday, for Presidents’ Day.

The installation of our deep foundation will continue to be a 24-hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. This work will be most noticeable at various times over the next 6 weeks when the drilled foundations are installed on the 1st Street site. Neighbors should notice a reduction in noise starting around mid-March.

In late February, we will begin installing overhead pedestrian and vehicular protection on Ecker between Jessie and Mission Street next to the work site. This will require the full closure of Ecker to vehicular traffic for two weekends during the day. Ecker will continue to remain open to pedestrians at all times. Once the timeline is confirmed, notification regarding timing will be posted.

Feb 1, 2018 Update

The installation of our deep foundations will continue to be a 24-hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. This work will be most noticeable at various times over the next 6 weeks when the drilled foundations are installed on the 1st Street site. Neighbors should notice a reduction in noise starting around mid-March.

In mid-February we will begin installing overhead pedestrian and vehicular protection on Ecker between Jessie and Mission Street next to the work site. Exact dates are to be determined but this will likely require the full closure of Ecker to vehicular traffic for two weekends during the day. Ecker will continue to remain open to pedestrians at all times.

Over the next several weeks, Oceanwide’s contractors will continue the installation of the perimeter shoring wall on First Street. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

Jan 22, 2018 Update

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. This will continue to be a 24 hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, and we apologize for any inconvenience.

Oceanwide’s contractors have completed installation of the perimeter shoring wall directly behind One Ecker and they will continue the installation on the First Street side. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During this time, please feel free to contact the project’s general superintendent, Dave Thompson, directly at (406) 580-0152 or the 24-Hour hotline at (415) 746-9948.

Jan 8, 2018 Update

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. This will continue to be a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, and we apologize for any inconvenience.

Oceanwide’s contractors have completed installation of the perimeter shoring wall directly behind One Ecker and they will continue the installation on the First Street side. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During this time, please feel free to contact the project’s general superintendent, Dave Thompson, directly at (406) 580-0152 or the 24-Hour hotline at (415) 746-9948.

Dec 21, 2017 Update

Happy Holidays!  Oceanwide’s contractors will not be working the evening of December 23rd through the morning of December 26th and the evening of December 29th through the morning of January 2nd.

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. Unfortunately, this will continue to be a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, and we apologize for any inconvenience.

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site and is now on Stevenson and Ecker. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours.  Every effort will be made to minimize the impacts to all neighbors during this time.

Oceanwide’s contractors will continue minor demolition work on the southern part of Ecker Street between Mission and Elim. This work is preparation for installing overhead protection that is required for safe pedestrian passage down Ecker during construction.

During this time, please feel free to contact the project’s general superintendent, Dave Thompson, directly at (406) 580-0152 or the 24-Hour hotline at (415) 746-9948.

Nov 29, 2017 Update

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site immediately east of 1 Ecker along Stevenson Street. This work requires large steel beams to be delivered to the site for the next several weeks.  The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time. While this work continues, the temporary overhead pedestrian safety protection will remain in place on the south side of Stevenson.

Drilled pile work will transition over to the First Street site in the coming month.

We apologize for any inconvenience caused by night work and we will continue to make every effort to mitigate the impact to our neighbors.

Nov 17, 2017 Update

The temporary overhead pedestrian safety protection will remain in place on the south side of Stevenson for the next week.

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site immediately east of 1 Ecker. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During the installation of the shoring wall, drilled pile work will continue to be performed 24 hours a day as we complete the installation of the deep foundations on the Mission Street site and transition over to the First Street site in the coming month.

We apologize for any inconvenience caused by night work, and we will continue to make every effort to mitigate the impact to our neighbors.

During this time, please feel free to contact the project’s 24-Hour hotline at (415) 746-9948. Updates will also continue to be posted at www.swinertonwebco.wpengine.com.

Hello world!

Welcome to WordPress. This is your first post. Edit or delete it, then start writing!

Oct 27, 2017 Update

The temporary overhead pedestrian safety protection has been installed on the south side of Stevenson. We expect that it will remain there for the next several weeks.

Last week’s update noted that work would begin on the perimeter shoring wall this past Monday. Oceanwide had additional prep work to complete and this work did not begin as planned. The work will begin Monday, October 30. Oceanwide’s contractors will install the perimeter shoring wall on the First Street site immediately east of 1 Ecker. This work will require large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During the installation of the shoring wall, drilled pile work will continue to be performed 24 hours a day as we complete the installation of the deep foundations on the Mission Street site and transition over to the First Street site in the coming month.

We apologize for any inconvenience caused by night work and we will continue to make every effort to mitigate the impact to our neighbors.