Dec 21, 2017 Update

Happy Holidays!  Oceanwide’s contractors will not be working the evening of December 23rd through the morning of December 26th and the evening of December 29th through the morning of January 2nd.

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. Unfortunately, this will continue to be a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, and we apologize for any inconvenience.

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site and is now on Stevenson and Ecker. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours.  Every effort will be made to minimize the impacts to all neighbors during this time.

Oceanwide’s contractors will continue minor demolition work on the southern part of Ecker Street between Mission and Elim. This work is preparation for installing overhead protection that is required for safe pedestrian passage down Ecker during construction.

During this time, please feel free to contact the project’s general superintendent, Dave Thompson, directly at (406) 580-0152 or the 24-Hour hotline at (415) 746-9948.

Nov 29, 2017 Update

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site immediately east of 1 Ecker along Stevenson Street. This work requires large steel beams to be delivered to the site for the next several weeks.  The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time. While this work continues, the temporary overhead pedestrian safety protection will remain in place on the south side of Stevenson.

Drilled pile work will transition over to the First Street site in the coming month.

We apologize for any inconvenience caused by night work and we will continue to make every effort to mitigate the impact to our neighbors.

Nov 17, 2017 Update

The temporary overhead pedestrian safety protection will remain in place on the south side of Stevenson for the next week.

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site immediately east of 1 Ecker. This work requires large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During the installation of the shoring wall, drilled pile work will continue to be performed 24 hours a day as we complete the installation of the deep foundations on the Mission Street site and transition over to the First Street site in the coming month.

We apologize for any inconvenience caused by night work, and we will continue to make every effort to mitigate the impact to our neighbors.

During this time, please feel free to contact the project’s 24-Hour hotline at (415) 746-9948. Updates will also continue to be posted at www.swinertonwebco.wpengine.com.

Oct 27, 2017 Update

The temporary overhead pedestrian safety protection has been installed on the south side of Stevenson. We expect that it will remain there for the next several weeks.

Last week’s update noted that work would begin on the perimeter shoring wall this past Monday. Oceanwide had additional prep work to complete and this work did not begin as planned. The work will begin Monday, October 30. Oceanwide’s contractors will install the perimeter shoring wall on the First Street site immediately east of 1 Ecker. This work will require large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours. Every effort will be made to minimize the impacts to all neighbors during this time.

During the installation of the shoring wall, drilled pile work will continue to be performed 24 hours a day as we complete the installation of the deep foundations on the Mission Street site and transition over to the First Street site in the coming month.

We apologize for any inconvenience caused by night work and we will continue to make every effort to mitigate the impact to our neighbors.

Oct 19, 2017 Update

Next week, Oceanwide’s contractors will begin installing the perimeter shoring wall on the First Street site immediately east of 1 Ecker. This work will require large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and 5:00 am so the beams will be delivered during these hours.

Every effort will be made to minimize the impacts to all neighbors during this time. During the installation of the shoring wall, drilled pile work will continue to be performed 24 hours a day as we complete the installation of the deep foundations on the Mission Street site and transition over to the First Street site in the coming month.

We apologize for any inconvenience caused by night work and we will continue to make every effort to mitigate the impact to our neighbors.

Aug 28, 2017 Update

Oceanwide or its designated contractors will continue prep work for backfilling soil against the basement wall on the east side of One Ecker. The prep work protects the recently installed waterproofing and the structural integrity of the basement wall. Protection and backfilling will continue during daytime work hours for the rest of the month. We had originally anticipated that the backfilling would begin in August, but the expected start date has been moved to late September. One Ecker residents and other impacted neighbors will be further notified before Oceanwide begins backfilling in this area.

Oceanwide’s contractors will continue installing foundation piles for the Mission Street Tower until late fall. This work will require some additional night work. Unfortunately, this is a 24-hour-a-day operation, as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue to make every effort to limit the impact of this work, and we apologize for any inconvenience.

Demolition of building 78 is complete.

July 14, 2017 Update

Continuing until late fall, Oceanwide’s contractors will be installing foundation piles for the Mission Street Tower. This work will require some additional night work. Unfortunately, this is a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will do our best to limit impacts, and we apologize for any inconvenience.

Oceanwide or its designated contractors will continue prep work for backfilling soil against the basement wall on the east side of One Ecker. The prep work protects the recently installed waterproofing and the structural integrity of the basement wall. Protection and backfilling will begin in August during daytime work hours. Residents will be further notified in advance of the operation.

Partial demolition of building 78 will continue during the hours of 7:00 am – 5:00 pm. The demolition is now on the 2nd floor. We anticipate that the demolition will be completed by the end of August.

July 7, 2017 Update

We hope you had a happy and safe 4th of July!

Beginning in early July and continuing until late fall, Oceanwide’s contractors will be installing foundation piles for the Mission Street Tower. This work will require some additional night work. Unfortunately, this is a 24-hour-a-day operation as the type of foundation that we are installing requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will do our best to limit impacts, and we apologize for any inconvenience.

In preparation for upcoming work at the 1st Street Tower, Oceanwide or its designated contractors has added additional waterproofing and will be providing additional protection to the basement wall of One Ecker. This work will include the installation of sheet piles along the perimeter and backfilling this area to provide additional support. This work will take place during daytime hours, and we apologize for any inconvenience during this time.

Partial demolition of building 78 will continue during the hours of 7:00 am – 5:00 pm. Streetlight upgrades will be finalized in this area this week.

June 29, 2017 Update

Beginning in early July and continuing until late fall, Oceanwide’s contractors will be installing drilled foundation piles along the Mission Street site 24 hours a day. The foundation piles go all the way into bedrock, and the process of drilling and pouring concrete must be done in a 24-hour cycle and requires working at night. We will do our best to limit neighborhood impacts throughout this entire process.

Partial demolition of building 78 will continue during the hours of 7:00 am – 5:00 pm. Additionally, streetlight upgrades will take place in this area during regular business.

June 26, 2017 Update

Oceanwide has completed Ecker Street pedestrian safety improvements. Ecker Street between Jessie and Mission is now open to southbound traffic. Both cars and pedestrians will have access to this portion of Ecker Street for the duration of construction. For safety, pedestrians should use the newly installed sidewalks when walking down Ecker Street.

Beginning next week, Oceanwide or its’ contractors will be moving heavy equipment into the Mission Street site. This work will take place from 5:00 am – 8:00 pm.

Partial demolition of building 78 will continue during the hours of 7:00 am to 5:00 pm. Additionally, streetlight upgrades will take place in this area during regular business.

On July 1 and July 3, drilling work will occur along Elim Alley, on the south side of 25 Jessie Street.  This work will take place between 7:00 am and 5:00 pm.